top of page

CIVIL CONSTRUCTION

Construction of Major Culvert Renewal Merrigum - Ardmona Road, Merrigum

Project Start/Finish Date: June to July 2024

Client: Greater Shepparton City Council

Decommissioning & removal of existing culvert crossing structure & existing road pavement, construction of a new 1200x900 six cell culvert crossing structure with guard railing over waterway, reinstatement of road infrastructure.

Murray Valley West Drainage Course Declarations - Obstruction 32 & Obstruction 33

Project Start/Finish Date: April to May 2024

Client: Goulburn Murray Water

Removal of existing 600mm x 300mm box culvert from Murray Valley Highway and installation of 2 rows of box culverts each 1200 wide x 450 high x 20400 long. OB32 included the removal of an existing small pipe from under a farm channel, installation of a new syphon and remodelling of the farm channel termination banks. The works included open trenching, culvert and headwall laying, pipe laying, road sealing and excavation, rock beaching and civil works.

Nagambie-Locksley Road Bridge and Road Reconstruction at Charles Creek Locksley Stage 1

Project Start/Finish Date: March to June 2024

Client: Strathbogie Shire Council

Bridgeworks

Demolition of entire existing two-span bridge. Construction of bridge foundations including abutments. Supply and Installation of precast concrete deck PSC Planks, cast-in-situ concrete deck overlay and concrete approach slabs, rock beaching and erosion protection works and Installation of bridge barriers.

Roadworks

Construction of earthworks and excavation for pavement construction. Supply and placement of fill material to construct road formation. Supply and lay bitumen and aggregate pavement. Supply and placement of crushed rock as per the road pavement profiles. Supply and installation of approach guardrail and terminals. Reinstatement of batters and disturbed areas. Supply and installation road signage. Topsoil batter slopes and seed.

190 Bay Carpark and Access Road Construction, Cobram

Project Start/Finish Date: January to April 2024

Client: Moira Shire Council

Stage 1, Cobram - Realignment of existing services and storm water drainage pipelines, removal and disposal of existing kerb and channel, concrete paths, bituminous surfacing and pavements, installation of 630m of concrete kerb and 400m2 of paths, construction of retaining wall and flashing, installation of stormwater pits and 70m of pipework, electrical conduits and pits, construction of 5,250m2 of crushed rock pavements and Type N asphalt wearing course, line marking, installation of 90 bollards and landscaping.

Axedale-Toolleen Road Widening and Rehabilitation Works, Toolleen

Project Start/Finish Date: December 2023 to March 2024

Client: Campaspe Shire Council

Widening and rehabilitation of existing 1.5km road pavement including the installation of a TL4 road barrier and end terminals, lime and cement subgrade stabilisation, 4 no. driveway crossings, 3 no. box culvert road crossings, 14/7 spray seal, line marking.

Midland Highway/Carag Road/Robertson Road Interchange Upgrade, Carag Carag

Project Start/Finish dte: September to November 2023

Client: Private Client/VicRoads

Road Installation of additional turning lane on Midland Highway. 

Works included new pavement, upgrade of existing pavement, culvert extentions and barriers.

Construction Florence Street Slip Lane

Project Start/Finish Date: March to June 2023

Client: Greater Shepparton City Council

Construction of new slip lane turning left from Florence Street into Benalla Road, Shepparton.

Demolition of existing infrastructure, civil upgrades and road resurfacing, traffic signals, stormwater drainage, electrical and telecommunication works, water main upgrades, line marking, concreting and footpath works, landscaping.

Welsford Street Stage 4 Upgrade, Fryers Street Intersection, Shepparton

Project Start/Finish Date: December 2022 to March 2023

Client: Greater Shepparton City Council

Reconstruction of Welsford Street, between the intersections of Nixon and Fryers Street, and the re-construction of Fryers Street, between Welsford Street and Midland Highway, Shepparton. 

10,430m2 of pavement (full depth asphalt & flexible), 760m2 of concrete pavement, 1050m of kerb, re-signalisation civils and electrical, RCP drainage & pit installation, supply & install of 6 no. tree cells and TGSI installation.

Munarra Stadium and Precinct

Location: Shepparton

Client: Greater Shepparton City Council

Construct storm water drainage system, 1.1km of 1350mm dia RCP deep drainage, 32,000m3 detention basin, 7.3km deep pre-cast stormwater pump station, 400m2 dioretention rain garden, 26 pits, clay liner, topsoiling and fencing.

Skilton Ave, 28 Lot Subdivision, Tatura

Project Start/Finish Date: January 2022 to December 2022​

Road pavement construction, kerb and channel, RCP and pit install, electrical, comms, water and sewer installation works.

Shepparton Corridor Upgrade Project

Project Start/Finish Date: August 2021 to March 2024

Client: Coleman Rail

Nagambie Turnout Formation Works

Bulk Earthworks for Nagambie Yard, Lime Stabilisation, Structural and capping and ballast placement, Track Drainage

Murchison East Loop

Earthworks – Strip Topsoil and Organic material, Bulk Earthworks and Subgrade Preparation, Track Formation Works.

Drainage - Construct and installation of new formation and access track cess drains. Drainage was installed across the Murchison Passing Loop.

 

Stabling Yard, Mainline Slew and Turn out

Earthworks - Strip Topsoil, Bulk Earthworks – Cut to Fill and load out of excess material, Lime stabilization, Place and compact – Structural Fill, Capping Bottom Ballast.

Drainage - RCP Pipe, Cess Drainage, Cross Track Culverts, Subsoil Drainage, Intertrack Drainage.

Piling -Bored Piling works (including placement of Pile cage & rag bolt sets, Services Gantry Piles, Light pole and CCTV piles, Amenities Building Slab and footings, Storage Building slab and footings.

Nagambie - Civil and Formation Works, March Occupation

Mudspot Rectification, Level Crossing Civil Works, Occupation Crossing Works.

Construction of Karibok Park - Retardation Basin and Recreational Area, Shepparton

Project Start/Finish Date: August 2021 to January 2022​

Client: Greater Shepparton City Council

  • Earthworks & Basin Construction

  • Drainage

  • Rockworks

  • Fencing

  • Reinstatement Works

Murray Valley Highway/Lady Augusta Road – Intersection Upgrade Works, Echuca

Project Start/Finish Date: August 2021 to October 2021​

Client: VicRoads

  • Earthworks – Excavation of approx. 601m3 of existing material, place and compact Type B fill, regrade of existing shoulders.​

  • Drainage Works – Install 43Lm of 450dia RRJ drainage, 12Lm Box Culverts, SD1981 Wingwalls and SD1991 and SD1992 Endwalls.​

  • Pavement Construction – Placed 173T of 100mm Class 1 size 20 crushed rock to shoulders, base course, 933T of 200mm Class 1 size 20 crushed rock, subbase, 1073T of 230mm Class 3 size 20 crushed rock, and 148m3 80mm Type A fill layer.​

  • Spray Bituminous Surfacing works - Placed over 7660m2 of 10/7mm emulsion primerseal and 14/7mm XSS final seal, Line marking, RRPM’s and reinstall/install guideposts, installation of new signs, Flexible W-beam and GREAT terminals.

Salvation Army Carpark, Shepparton

Project Start/Finish Date: May 2021 to September 2021​

Client: GMR Engineering Services

Construction of Car Parks – Kerb & Channel and Drainage works

Earthworks, Demolition & Preparation, Car Park Lighting, Stormwater Drainage, Pavement & Surfacing, Concrete Kerb & Paving, Traffic Management, Site Reinstatement

Northern Native Fish Hatchey, Arcadia

Project Start/Finish Date: January 2021 to June 2021​

Client: Victorian Fisheries Authority

Works Included:

  • Construction of 32 new Plankton and Brood stock ponds including the placement and compaction of 26,000m3 fill to form new embankments

  • Installation of 3,250m of DN200-225mm PVC-M pressure pipelines and valves

  • Installation of 4,000m of electrical and communication conduits and 26 pits

  • Construction of below ground concrete harvest facility

  • Installation of steel walkway structures and drainage sumps

Greater Shepparton Secondary College, Shepparton

Project Start/Finish Date: April 2020 to 2022

Client: Hansen Yuncken Pty Limited

​​

  • Civil Works

  • Drainage

  • Car park construction including base, kerb and asphalting

  • Busway construction

  • Hardstands

  • Lime stabilisation of subgrade

  • Detailed footing excavation

Construction of Wyndham Street & Fitzjohn Street Intersection Upgrade, Shepparton

Project Start/Finish Date: ​November 2020 to February 2021

Client: Greater Shepparton City Council

  • Road Widening and Intersection Upgrade Works

  • Replacement of kerb and channel

  • Reconstruction of existing pavement, drainage, kerb and channel

  • Railway Corridor Works

  • Supply and Installation of traffic lights

  • Traffic and Pedestrian Management

  • Landscaping

Widening Works

Wyndham Street

Intersection Works

Construction of Yakka Basin, Shepparton

Project Start/Finish Date: March - August 2020​

Client: Greater Shepparton City Council

  • Earthworks associated with the removal of 45,000m3 of material,

  • Deep RCP and Pit Drainage runs

  • Bio-retention swale drain and rockworks 

  • Supply and install new pumping station and DN150 rising main

  • Filtration system

  • Clay liner construction 

  • Top soiling, Landscaping and Hydroseeding

  • Fencing installation

BP Service Station, Jeriderie

Project Start/Finish Date: November 2019​

Client: Becon Constructions (Aust) Pty Ltd

Civil works for large service station including large truck facilities:

  • Excavation to subgrade level across site

  • Install crush rock base of concrete works

Latham Road Upgrade

Location: Echuca, Victoria

Client: Shire of Campaspe

Construction of 2.119 kilometres of Latham Road east from Braund Road including:

  • Earthworks and construction of crushed rock pavement with a 6.4m wide pavement, 6.2m wide two coat seal, linemarking and signage

  • Construction of cross road drainage culverts and wayside table drains

  • Cement stabilisation of pavement sub-base through floodway

  • Installation of entrance culverts at all existing driveways

  • Traffic Management to enable road to remain open at all times during the works

St Mary's Carpark, Seymour

Location: Seymour, Victoria

Client: St Mary's College

Construction of new school entry and staff/ visitor carpark outside new administration building including:

  • New entry onto High St

  • Construction of 2440m2 asphalt carpark  - Primer and 40mm Hotmix

  • Construction of storm water drainage system, side entry pits and installation of oil water separator,

  • Kerb and Channel

  • Footpaths

bottom of page